Bug report
The menu that determines where to add new task incorrectly appears after creating a new task and editing an existing one.
Reproduction of the problem
- Open this Dojo example - https://dojo.telerik.com/uBAHUgOy
- Add new task.
- Randomly edit another task so that no item is selected in the Gantt TreeList.
- Press the Add Task button again.
Current behavior
The Add Child/Above/Below menu appears unexpectedly.
Expected/desired behavior
The menu should not appear and a new task should be added at the bottom of the list.
Environment
- Kendo UI version: 2021.2.616
- Browser: [all]