The dependencies in the Gantt can not be removed.
Nothing happens, there is no confirmation popup, and the dependency is not removed.
A confirmation dialog for confirming the deletion appears and the dependency should be removed.
When the autoSync option of the GanttDependencyDataSource is set to true, two identical requests are sent to the server when creating a new dependency.
Two identical Create requests are sent to the server
Only one request should be sent to the server
i hope i can configure working day and off day
If you expand/collapse the top parent node, it is marked as dirty.
Regression introduced with R1 2023
The top node is marked as dirty when collapsed
The top note shouldn't be marked as dirty upon collapsing
It would be nice if tasks could be added to gantt that are missing a start date, end date or both dates. For our use case this feature is not only useful, but mandatory. We are visualising a project workflow that goes through several phases and steps. Within our application, the client fills in the dates for these tasks and milestones as the project progresses. Not all dates are filled-in at all times, however when a project manager creates a gantt chart, he wants to see all the tasks. A task without a date is an information in itself. Currently we have to create a fake date entry for tasks without dates.
As all grids, the kendo Gantt chart's rows change their color when hovering. However, the background overlaps the border between columns and makes them disappear for the hovered row.
You can reproduce the described behavior by hovering one of the rows in this DOJO.
When there are Grid and Gantt on the same page and a column in the Gantt has reordered an error in the console is thrown:
kendo.all.js:133531 Uncaught TypeError: Cannot read properties of undefined (reading 'lockable')
The following error is thrown:
kendo.all.js:133531 Uncaught TypeError: Cannot read properties of undefined (reading 'lockable')
There should be no error in the console when reordering columns in Gantt, even if there is a Grid on the page.
Hi Team,
I would like to request a way to export a larger amount of records fast and easily with the Kendo UI Gantt. I have tried with over 800, but it runs sluggish. I am aware of the limitations, but would like to request a faster way to export to PDF.
Thank you!
Add a way to highlight the critical path in the Gantt Chart. This is a basic feature in project management and would be really great if you can implement,.
The change event incorrectly triggers at initialization of the Gantt - Regression with 2022.1.301
Also, the event does not trigger when selecting a task from the timeline - Regression with 2022.3.913
Change event triggers after initialization and does not trigger after selection in timeline
Change event shouldn't trigger after initialization and should after selection in timeline
When you collapse a selected task in the Gantt, the selection is lost
The selection is lost
The selection should be preserved
Incorporate page breaks into the Gantt PDF Export and include option to repeat column headers on each page.
Hi Team,
I would like to request the functionality to easily persist the state of the Kendo UI Gantt like in this Kendo UI Grid example. Maybe include getOptions/setOptions methods for the component.
Thank you!
Problem: We really want to fit Gantt's on particular paper sizes (def. landscape A3); however, using the paperSize option doesn't really work as the output (font size, row heights, etc.) end up being too big and not suitable. And for the majority of the time, paperSize set to auto creates an output (font size mostly) too small. Rock and a hard place... Solution 1: When pdf.paperSize is not set to auto i.e. A3, A4, etc. Allow a percentage scaling to be set, ideally individually, on X and Y. Solution 2: Scale fonts and scale timeline on X axis maintaining taskList width. Ultimately, get a large plan to fit on landscape A3.
In a Gantt that has a DropDownList as editor in the TreeList, if you click on the DropDownList's wrapper to open the widget, it will close the cell instead.
Regression introduced with 2022 R1
The cell closes.
The cell should remain open and the DropDownList should open
Hi,
Currently, you can change start OR end for the package without problems, and therefore you can change the duration this way, but for the project or phase, it is not possible.
Since these dates are changeable one by one manually through the table on the left or popup form, there is no logical reason why they can't be changed in the timeline as well.
Please could you consider adding this to the gantt widget.
Thank you very much.
When the duration of a task is edited in the Task Duration column in Gantt in the save event handler e.task.taskDuration returns the new duration value. With versions, before 2020 R3, the old task duration value has been returned.
With the current version, the new task duration is returned.
The returned e.task.taskDuration should return the previous task duration in order to be consistent with the behavior before 2020 R3
When the end date of a task is edited in the End Time column in Gantt in the save event handler e.task.end returns the new end date value. With versions, before 2020 R3, the old end task value has been returned.
The behavior is inconsistent with editing a task through dragging or by double-clicking on a task as in such case the previous value of the end task will be returned
With the current version, the new end date is returned.
The returned e.task.end should be consistent with the other ways of changing the date e.g. dragging or double-clicking on the task.