Hi,
The percent complete column does not work! If you use any other gantt product (including Microsoft project). When you enter the % complete, it's between 0 and 100, which is a universal standard around the world. % complete is never between 0 and 1. Please correct the Gantt tool to use the universal standard.
The usability of product will be much improved and users will like it.
Thank you!
David
Hello David,
As described in the Gantt API the percentComplete value could be between 0 and 1. Thus this could not be considered a bug. With that said, I am changing the type of the request to a Feature Request (instead of the 'Bug Report').
Note, that you could use the editable.template configuration option and provide the custom template for the Gantt editor. In the template, you can configure the NumericTextBox to increase/decrease the values with 1. Here is such a small dojo example.
Regards,
Neli