Last Updated: 24 Mar 2020 09:55 by ADMIN
Helen
Created on: 03 Oct 2017 16:00
Category: Gantt
Type: Feature Request
4
Gantt: Add time-based weighting into percent complete calcs
Currently % complete calcs for summary tasks are based solely on the sum of % complete per child task / number of child tasks (x%+y%+z%)/3.   In this way, a small scale task of 1 or 2 days has a large impact on summary % complete whereas a large task of 60 days has a small impact.  Request is to add in weighting based on duration (end date - start date).
0 comments