I was trying out the RadGantt control. Noticed the following

1. There is no validation on the dependency - for example, if I have set the dependency to "Start After" parent task, then should it allow me to enter CompletionPercentage? does not make sense.

2. If I extend the end date of the predecessor, then there is no option to automatically update the dates of all successors. This means that I have to manually adjust all the subsequent dates. Doe not make sense.

These were noticed on the demo application on the web. If these features exist, then please point me to the relevant demo.