Describe the bug
When boostrap.min.css is loaded on the page, the positioning of the Gantt tasks within the task rows is incorrect. The task are not centered and start overlapping the next row. Additionally, misalignment between the rows in the timeline and the treelist appears.
To reproduce
Steps to reproduce the behavior:
https://dojo.telerik.com/AYeWOkIX
The misalignment increases with each next row, so it becomes more evident, if you scroll down the view.
Expected behavior
Tasks are centered within their row. Timeline and treelist rows are aligned.
Affected package (please remove the unneeded items)
Affected suites (please remove the unneeded items)
Affected browsers (please remove the unneeded items)
Build system information (please remove the unneeded items)
Additional context
Add any other context about the bug.