Unplanned
Last Updated: 27 Aug 2024 12:12 by Eric

When the RowHeight of the Gantt is enabled and the planned tasks are shown, the height of the row in the timeline is miscalculated and that creates displacement. 

Additionally, the task dots used for the dependencies are misplaced in the same scenario as demonstrated in the dojo above. 

Unplanned
Last Updated: 26 Jul 2024 07:11 by ADMIN

When a user switches from navigating by mouse to navigating by keyboard, the focused element in the overview grid is not synchronized. Please follow the instructions below to reproduce the issue using this DOJO:

  • click e.g. on the first cell in the "id" column
  • using your arrow keys, move the keyboard focus to the last cell of the "id" column
  • click the checkbox in the first row (keyboard focus is now lost)
  • press the enter key (keyboard focus reappears in the last cell of the "id" column)

Wouldn't a user expect the cell he/she just clicked to be focused? The keyboard focus should be updated even when navigating by mouse.

 

Unplanned
Last Updated: 25 Jul 2024 07:46 by ADMIN

When rendering this minimal DOJO containing a Kendo-UI Gantt chart in Chrome, space in the grid header is reserved for the vertical scrollbar on the right hand side:

When using Firefox, space is still reserved, although scrollbars collapse by default and therefore do not need any space:

Unplanned
Last Updated: 21 Jul 2024 22:08 by oomaccounts
Created by: Sujeet
Comments: 2
Category: Gantt
Type: Feature Request
4

Hi,

I am using kendo's Gantt chart. But I unable to achieve few things using the existing Gantt chart features.
Following are the features I request should be provided for Gantt chart:

  1. Multiple tasks/milestones in a row.
  2. Multiple rows for a parent task.
  3. If space is not available in preceding row(s), overlapping tasks should be moved to next row.
  4. User should be able to provide start date for the quarter in a fiscal calendar. Ex: If user give 01st-June as the start date, then Q1 should start from 01st-June. Hence, quarters will be defined as: Q1(June-Aug), Q2(Sept-Nov), Q3(Dec-Feb), Q4(Mar-May)

Gantt chart requirement point 1-4

Refer above image for point 1-4

 

       5. If task label is exceeding the width of the task, then height of the task should be increased to accommodate task label(in other words, text should            be wrapped). Also, font-size of the text should be responsive, that is, font-size should be reduced to accommodate entire text in minimum task height.

Gantt chart Requirements point 5

Refer above image for point 5

 

Unplanned
Last Updated: 05 Jun 2024 14:52 by Alan
Add capability to upload .mpp file and populate the GanttDataSource, GanttDependencyDataSource and Resource Assignments. Thanks.
Unplanned
Last Updated: 13 Mar 2024 13:20 by ADMIN
Created by: Michael D
Comments: 4
Category: Gantt
Type: Bug Report
0

As all grids, the kendo Gantt chart's rows change their color when hovering. However, the background overlaps the border between columns and makes them disappear for the hovered row.

You can reproduce the described behavior by hovering one of the rows in this DOJO.

Unplanned
Last Updated: 20 Oct 2023 10:02 by David
Created by: David
Comments: 0
Category: Gantt
Type: Feature Request
0

Bug report

Error is thrown in the console when an event is dragged.

Reproduction of the problem
Dojo: https://dojo.telerik.com/ORuSEYoW

Expected/desired behavior
Error shall not appear

 

Environment
Kendo UI version: [all]
jQuery version: [all]
Browser: all

Unplanned
Last Updated: 13 Jul 2023 06:21 by ADMIN
Created by: Peter
Comments: 2
Category: Gantt
Type: Feature Request
4
That is for scenarios when the start of one task is dependent on the end of another task. In such a case, if the end of the initial task changes, the start of the dependent task should also change automatically.
Unplanned
Last Updated: 19 Apr 2023 08:45 by n/a

Bug report

When the autoSync option of the GanttDependencyDataSource is set to true, two identical requests are sent to the server when creating a new dependency.

Reproduction of the problem

  1. Open this Dojo example - https://dojo.telerik.com/AGOJUyAp
  2. Open the Network Tab
  3. Create a new task dependency

Current behavior

Two identical Create requests are sent to the server

Expected/desired behavior

Only one request should be sent to the server

Environment

  • Kendo UI version: 2023.1.314
  • Browser: [all]
Unplanned
Last Updated: 17 Apr 2023 11:40 by Minas Gerais Administração
Created by: Imported User
Comments: 6
Category: Gantt
Type: Feature Request
8
i hope i can configure working day and off day
Unplanned
Last Updated: 05 Jan 2023 21:51 by Pochun
Created by: Pochun
Comments: 0
Category: Gantt
Type: Feature Request
1

Hi Team,

I would like to request a way to export a larger amount of records fast and easily with the Kendo UI Gantt.  I have tried with over 800, but it runs sluggish.  I am aware of the limitations, but would like to request a faster way to export to PDF.

Thank you!

Unplanned
Last Updated: 26 Dec 2022 18:19 by Washington
Created by: christer
Comments: 5
Category: Gantt
Type: Feature Request
25
Add a way to highlight the critical path in the Gantt Chart. This is a basic feature in project management and would be really great if you can implement,.
Unplanned
Last Updated: 06 Dec 2022 12:11 by ADMIN
Created by: Imported User
Comments: 10
Category: Gantt
Type: Feature Request
25
Incorporate page breaks into the Gantt PDF Export and include option to repeat column headers on each page.
Unplanned
Last Updated: 16 Nov 2022 21:44 by Vishal
Created by: Vishal
Comments: 0
Category: Gantt
Type: Feature Request
1

Hi Team,

I would like to request the functionality to easily persist the state of the Kendo UI Gantt like in this Kendo UI Grid example.  Maybe include getOptions/setOptions methods for the component. 

Thank you!

Unplanned
Last Updated: 10 Oct 2022 13:20 by Josh
Created by: Imported User
Comments: 2
Category: Gantt
Type: Feature Request
9
Problem: We really want to fit Gantt's on particular paper sizes (def. landscape A3); however, using the paperSize option doesn't really work as the output (font size, row heights, etc.) end up being too big and not suitable.

And for the majority of the time, paperSize set to auto creates an output (font size mostly) too small.

Rock and a hard place... 

Solution 1: When pdf.paperSize is not set to auto i.e. A3, A4, etc. Allow a percentage scaling to be set, ideally individually, on X and Y.

Solution 2: Scale fonts and scale timeline on X axis maintaining taskList width.

Ultimately, get a large plan to fit on landscape A3.
Unplanned
Last Updated: 29 Aug 2022 08:44 by ADMIN

Hi,

Currently, you can change start OR end for the package without problems, and therefore you can change the duration this way, but for the project or phase, it is not possible.

Since these dates are changeable one by one manually through the table on the left or popup form, there is no logical reason why they can't be changed in the timeline as well.

Please could you consider adding this to the gantt widget.

Thank you very much.

Unplanned
Last Updated: 04 Jul 2022 14:58 by Abilio
Currently, when a child task in the Gantt is edited the start/end time of the parent task will be updated accordingly. I would like to have the possibility to disable this behavior and have the possibility to edit the child's tasks' start and end times without updating the start and end times of the parent task.
Unplanned
Last Updated: 08 Mar 2022 08:41 by Magnus

Bug report

When a value in the TreeList nested in the Gantt is edited and is initially selected using the mouse, the save event is fired, but the e.values is undefined. Also, the value is changed back to the initial one.

Reproduction of the problem

  1. Open the Dojo - https://dojo.telerik.com/@NeliKondova/arUgAguv
  2. Click in the 'Task1' cell to edit and mark the entire text using the mouse
  3. Type some text and press 'Enter' - The issue will not be replicated in case the edited mode is exited through clicking in another cell, but only by pressing Enter.
    screencast

Current behavior

The Edit and Save events are fired. The value of the e.values in the save events is undefined. The value of the cell is changed back to the initial one.

When the value of the cell is not marked initially with the mouse, but the user starts typing immediately after clicking in the cell the issue is not replicated. Also, only the Save event is fired and the new value is present in e.values

Note: The issue might be related to the following behavior in the TreeList: When the steps described above are followed in the TreeList - the save event is fired, but actually the edited mode is not exited - Dojo

Expected/desired behavior

The behavior should be consistent. The same events should be fired in case the edited mode is exited by pressing 'Enter' and by clicking in another cell and e.values should contain the updated value.

Environment

  • Kendo UI version: 2022.1.301.
  • Browser: [all ]
Unplanned
Last Updated: 04 Mar 2022 21:08 by Austin
Created by: Austin
Comments: 0
Category: Gantt
Type: Feature Request
1

Hi Team,

I would like to request an easy, built-in way to format the dateTimePickers with the popup editor for the Kendo UI Gantt.  Currently, the validation will not allow for the editor to be set to a specific format without creating a dedicated editable.template.

Thank you!

Unplanned
Last Updated: 31 Jan 2022 13:27 by ADMIN
Created by: Stoyan
Comments: 0
Category: Gantt
Type: Feature Request
0
When summary/parent tasks in the Gantt are edited in the timeline the duration of the parent task is not always consistent with the net duration of its children.
Please review this Screen capture for the described behavior: https://www.screencast.com/t/la1PzVZaYc


This issue can be avoided, if the duration of the parent tasks can be configured to be fixed. Then the parent task's duration will only be dependant on the duration of its children.

Furthermore the timeframe of the parent task would be editable by changing the starting date.
1 2 3